Proposal B - Proposed by ASPI Group & ASPI's National Development Partners

1. Business Specifications

Project Name
Aerospace Manufacturing Building
Location
Tyndall Road near the corner of Stratford Road in Moses Lake, Grant County, Washington
Lot Size
10 Acres
Area Size
Total rentable area (Warehouse & Office): 100,000 sq ft
Term
Fifteen / Twenty year lease term
Zoning
The proposed parcel is zoned I-H Heavy Industrial located in Grant County, Washington

* Call to inquire the Base Rent, Tenant Improvements & Other Details

2. Building Specifications

Heating & Ventilation
Gas fired unit heaters to provide freeze protection per Washington State Code
Column Spacing
Approximately 50' x 50' & building 250' (W) x 400'(L)
Ceiling Height
Minimum 24'
Fire Protection
ESFR fire protection system
Floor
6" thick concrete slab, 4000 psi, #4 rebar
Roof
Metal deck on metal girders, R-19 insulation
Truck Loading
Three drive-in overhead loading doors at 12' x 14', & ten 9' x 10' dock high doors
Lighting
400 watt, metal halide, high bay lighting
Power
2,000 amp building severice
Water
City of Moses Lake
Sewer
City of Moses Lake
Natural Gas
Grant County PUD
Fiber Optic / Telephone
Reliable and redundant fiber is provided

Schedule

Critical Path Activities
Milestones
Lease agreement & schematic design
30 days
Preliminary shell plan & specification
30 days
Grading permit
30 days
Shell construction
120 days
Manufacturing & office improvements
90 days
Punch list & equipment fit-up
30 days
Total critical path duration
330 days 11 months

@

Non Critical Path Activities
Shell permit
60 days
Manufacturing & office design
60 days
Manufacturing & office permit 150 days